Around 10.5 gigawatts of data centre capacity has been announced across the Iberian peninsula. Only about 4.5 gigawatts counts as active, meaning it is attached to an identifiable project with institutional capital behind it and a developer capable of building it. The other six gigawatts are announcements.
The binding constraint is not money and it is not land. It is grid capacity, network access and permitting, which are three different problems that arrive in sequence and each take years. A developer can close financing in months and then wait considerably longer for a connection point that physically exists.
Spain became attractive to this industry for good reasons. Electricity is comparatively cheap, the generation mix is unusually renewable, and the land is available at prices that would be unthinkable in Frankfurt or Dublin. Those advantages are real and they are all downstream of a grid that was not built with gigawatt scale single sites in mind.